Introduction: true story (with pictures)

Page 4

The Project in Pictures, continued

M11 Feb49BnsSilos

Setting Bins and Silos: Progress end February 49%

M12 InstrElec

Instrument and Electrical: 12 February Start

M13 ChemClean

Chemical Cleaning: 14 March Start

M14 March54

Progress end March: 54%; Peak Labor Force March 29 at 1,223 workers

M15 April69

Progress end April: 69%; also peak monthly progress: 14.9%

note: the letters on the large bridge-crane in the background are three stories high – this was reputedly the largest crane in the world at the time (although not needed on our modules)

M16 Arch

Architectural / Siding: 05 May 1983 Start; Progress end May: 79%

M17 June85

Sea Fastenings / Tie-downs: 05 June Start; Progress end June 85%

One Comment

  1. Justin Smith
    Posted August 28, 2007 at 4:21 am | Permalink

    I found the summary of this posting (page 8) very useful. It is clear that you have a lot of good insight into the oil industry. I would like to learn more about the political pressures -internal and governmental- your projects faced, and your recommendationed solution for overcoming/circumventing these obstacles.

Post a Comment

Your email is never published nor shared. Required fields are marked *

*
*