Project Scope in numbers:

Number of Modules 28

Total Module Weight 14,300 MT

Direct Field Manhours 2,130,000 mhrs

Construction Drawings and Isometrics 4,400 drawings

Mechanical Equipment 1,300 items

Tagged Instruments 4,750 tags

Valves and Fittings 31,200 items

Pipe 29,300 meters (17 miles)

Electrical Conduit 50,000 meters (28 miles)

The Project in Pictures:

M01 Baseframes

Base Frame Girder Fab: 07 July 1982 Start; 20 Nov Complete

M02 Baseframes

Base Frame Assembly: 10 Aug Start; 31 Dec Complete

M03 PipeFab

Pipe Fab: 25 September 1982 Start; 20 May 1983 Complete

M04 Superstructure

Superstructure Cutting: 26 October Start

M05 SSPreFab

Superstructure Panels Prefabrication: 23 November Start

M07 OFE

Owner Furnished Equipment: First Module Complete Jan 1983; Last Module Complete March 1983

M08 Equip

Equipment Setting: 08 January 1983 Start

M09 PipeErec

Pipe Erection: 08 January 1983 Start

M10 ProgressJan38

Progress end January: 38%

One Comment

  1. Justin Smith
    Posted August 28, 2007 at 4:21 am | Permalink

    I found the summary of this posting (page 8) very useful. It is clear that you have a lot of good insight into the oil industry. I would like to learn more about the political pressures -internal and governmental- your projects faced, and your recommendationed solution for overcoming/circumventing these obstacles.

Post a Comment

Your email is never published nor shared. Required fields are marked *

*
*